Skip to main content
RoadsDBFM / availability payment

Lviv Northern Bypass

Lviv, Lviv Region

Lviv Northern Bypass
Feasibility Study

Information is current as of September 18, 2026

Key indicators

PPP Model
DBFM / availability payment
Estimated Investment
$335-410M
Concession Period
15-20 yrs
Readiness Status
Feasibility Study
Preparation Progress65%

About the project

The greenfield project focuses on the construction of the Lviv Northern Bypass and the provision of long-term maintenance of the road and associated infrastructure over the project term. The project comprises 23.2 km of new high-capacity road, forming the northern section of the Lviv ring road, connecting M-06 (Kyiv-Lviv-Chop), M-09 (Lviv-BCP "Rava-Ruska/Hrebenne") and M-10 (Lviv-BCP "Krakovets/Korczowa" via T-14-14).

Key facts

  • Strategic greenfield bypass creating a missing northern section of the Lviv ring road, enabling full redistribution of transit traffic around the city
  • Infrastructure link connecting M-06 with M-09, M-10 and M-11, integrating major national and international transport corridors around Lviv
  • Expected to redirect transit traffic from the Lviv urban network, redistributing north-south traffic flows along optimal routes without entering the city
  • Brings positive economic value and Value-for-Money compared to traditional procurement

Scope of works

  • 23.2 km of new construction from T-14-14 to M-06, including 21.4 km of Category I-a four-lane road and 1.8 km of Category II four-lane road
  • Required minimum 4 years for completing design and construction

Project status

  • Planned to be implemented as an availability-payment-based PPP
  • Design documentation ready, now being updated
  • Land mostly secured

Key private partner’s responsibilities

  1. Receiving relevant approvals
  2. Financing for initial capital investments
  3. Design
  4. Road rehabilitation works
  5. Road maintenance in accordance with contracted KPIs

Next steps

  1. Finalize concept note
  2. Develop feasibility study and perform efficiency analysis
  3. Tender preparation
  4. Tendering

Other projects in this sector

National Weight-in-Motion (WIM) System
Feasibility Study
M-09/M-10/M-11 Road Corridor
Feasibility Study
$600-730M15-20 yrs
M-07/M-19 Road Corridor
Preliminary Feasibility Study

M-07/M-19 Road Corridor

Lutsk, Volyn Region

$300-360M15-20 yrs