Second Terminal of the Port "Chornomorsk"
Chornomorsk, Odesa Region
Feasibility Study
Information is current as of September 18, 2026
Key indicators
- PPP Model
- Concession
- Concession Period
- 35 yrs
- New Jobs
- 180
- Readiness Status
- Feasibility Study
Preparation Progress45%
About the project
The second terminal has a cargo turnover potential of up to 1.6 million tons per year. The concession will create new jobs and unlock transshipment potential for a range of cargoes, such as grain, oil, building materials and containers.
Investment commitments
To be determined based on the results of the feasibility study. An increase in cargo handling volumes to 1.6 million tons per year is expected.
Assets to be transferred to the concession
CSPC:
- Real estate objects within berths No. 7-9 (administrative and service buildings, etc.), drawbridges, machinery and equipment, other assets
USPA:
- Berths No. 7-9
- Buildings, transformer substations, engineering networks, other infrastructure
- Machinery and equipment, other assets
Expected results
- ~180 new jobs
- Increase revenues to the state and local budgets